ORIO Toe Prep

The TEAM Oil Tools Toe Prep System utilizes the field proven ORIO™ Toe Sleeves. The system enables the Operator to both test their casing, then open the entire stage 1. This quick process eliminates the first plug and gun run in a multi-stage completion. This entire process can take place with the frac spread being mobilized on location. Secondary stages can also be quickly opened with TEAM’s ball activated ORIO™ XL system.

Procedure:

  • Install TEAM Oil Tools ORIO™ Toe Sleeves
  • Cement lateral per standard operations
  • Pressure test casing per Operator procedure
  • Open multiple toe sleeves with hydraulic applied pressure
  • Establish an initial injection and stimulate stage 1
 
 

Contact Us

Unique problems require unique solutions. Let our team of experts offer advice on the
best way to tackle your downhole challenges.